Breakdown of the Project
It was a privilege to be approached by Northumbria Wildlife Trust with the trust being local to our head office. The representative requested a 2-stage quotation, with stage 1 being the fabrication work and stage 2 for the internal fit out for a bespoke bide hide viewing container. We met on site at our conversions depot to showcase current projects that were in production, and had similar attributes.
After agreeing to go ahead with stage 1, the team at the wildlife trust provided us with basic drawings with dimensions and positioning for the hatches and personnel door. The order was placed and we then provided 3D rendered visuals to give the team a visual of what the final converted container will look like. The fab work progressed and we met the representative on site during the build and after meeting we added additional gas struts for the lift up hatches. After the official sign off the unit was delivered to site where the customer commenced with the internal fit out.